DEFECT MANAGEMENT

DEFECT MANAGEMENT PROCESS ON TANKER VESSELS


Definition.

Before we start talking about the defect, let us first understand what defect is, in tanker industry defect is usually defined as:

"Any damages/breakdowns on critical equipment outside of planned maintenance that cannot be immediately repaired on board using existing spares and resources, i.e. require assistance/advice from office or third party."

Everything else falls under the category of unscheduled /corrective job or straight forward repair.


Defect management.

As far as tanker vessel maritime industry goes, defects are managed mostly by use of integrated software management system, i.e. Marine ERP that contains PMS.

The defect management process usually consists of four steps.

     The process starts when the vessel has a breakdown of critical equipment, then in software vessel creates defects and informs the office.
      The defect, as a rule, is always proposed by the vessel. Before opening a defect, the vessel management team will identify, by use of Risk assessment process, the risk involved in that defect and will implement risk-mitigating factors. Results of the Risk assessment will be used for Risk level notation of the defect.
     The Risk level is noted using the following wording: LOW-RISK DEFECT, MEDIUM RISK DEFECT and HIGH-RISK DEFECT each notation is obtained by using Risk assessment and getting results by implementing risk-mitigating factors.
     
     By Completing  all of the above the vessel sends defect proposal to the office, and that is when the next step in the defect reporting process and management starts.
     Here the Technical superintendent in charge of the vessel reviews the defect and checks all the corresponding documentation. The documentation consists of, but it is not limited to, Risk assessment, Root cause analysis (identifying what caused the defect in the first place), proposal to avoid reoccurrence, requirements for fixing the defect together with additional documents and photos.
      In step three, the vessel obtains feedback on a proposed defect ( Accepted, rejected, approved, acknowledged). In case of approval also proposed, and an approximate date for fixing the defect and getting equipment back online is given. If the due date for the defect is too far away and normal working condition cannot be obtained soon, temporary management of change should be implemented until the defect is closed, i.e. equipment condition restored to normal.
      In step four, the final step, the vessel is closing defect providing objective evidence together with comments and providing date completed. Defect becomes closed, and that means that all is done. When closing the defect, the extensive reason must be given, e.g., repairs and service reports, photos etc.

      Important

     The above process requires ship and office staff to communicate through all available channels, to ensure all are aware of the defect and of the measures to resolve the same (including near miss reporting, accident reports and typical day to day communications as appropriate).

       Disclaimer:

         “ Out of Box Maritime Thinker” © 2018 and Aleksandar Pudar assumes no responsibility or liability for any errors or omissions in the content of this paper. The information contained in this paper is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness or of the results obtained from the use of this information. The ideas and strategies should never be used without first assessing your own company situation or system, or without consulting a consultancy professional. The content of this paper is intended to be used and must be used for informational purposes only.